§ 455.112. Davis-Bacon wage rate requirement.
98 words·~1 min read·
/us/cfr/t10/s§ 455.112·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
When an energy conservation measure or group of measures in a building, funded under this part, has a total estimated cost for acquisition and installation of more than $5,000, any construction contract or subcontract in excess of $2,000, using any grant funds awarded under this part must include:
(a)Those contract labor standards provisions set forth in 29 CFR 5.5 and
(b)A provision for payment of laborers and mechanics at the minimum wage rates determined by the Secretary of Labor in accordance with the Davis-Bacon Act (40 U.S.C. 276a) as set forth in 29 CFR part 1.
Connectionstraces to 1
Traces to 1 document
2 references not yet in our index
- 40 USC 276a
- 29 CFR 1
Citation graph
cites case law
Cites 3Cited by 0 across 0 sources